Monday, December 5, 2016
Friday, December 2, 2016
Backfill
BR Landscaping had three guys on site today to do backfill around the perimeter of the foundation and the garage. I can always breath a little more easily after this step has been completed. Any danger of dirt walls caving in or a flash flood setting us back are gone - nice!
Thursday, December 1, 2016
Waterproofing
Rock Concrete was in to complete their final task - waterproofing. The steps involve applying a bitumen layer, setting the weeping tile around the base of the footing, then installing the plastic waterproof membrane around the perimeter, followed by a good layer of at least 12" of gravel to allow for adequate drainage without dirt filtering down to block the weeping tile.
Tuesday, November 29, 2016
Stripping the forms
Ahh... walls! Rock Concrete was back in again this morning to strip the forms and reveal our walls. With the calcium added to the concrete under OBC rules, the concrete has cured very fast.
Monday, November 28, 2016
Friday, November 25, 2016
Ready to pour
The guys finished their forming work and rebar this morning, but the crappy weather means we are shifting the pour until Monday.
Thursday, November 24, 2016
Working in the rain
The walls were pretty much complete today and now we wait for a good window to pour. Tomorrow looks like a mixed bag forecast, so it may be pushed to Monday.
Wednesday, November 23, 2016
Forming begins
The guys from Rock arrived mid day after finishing their last house, and started preparatory work for the forming that they hope to complete tomorrow.
Tuesday, November 22, 2016
Monday, November 21, 2016
Footings repinned
GTA Surveying was in today to repin the wall locations while we stripped out all of the wood and garbage away from concrete footings.
Friday, November 18, 2016
Finally, we pour
Well, after an unsettling week of responding to phantom issues raised by an unknown neighbour [by the way, I've never understood people who call the City/Province/Parking/Police for the seemingly sole purpose of delaying the project and costing the owner of the house, their neighbour, more money...but I digress...], Rock Concrete was finally able to come in and pour the footings. Yeah!
Thursday, November 10, 2016
The other hole!
Everybody wants a walkout these days... whether it's for potential future rentals or just an excuse to rake more leaves...
Walkouts can be challenging, especially in an area like Etobicoke that has variably high water table levels depending where you are digging. Due to the fact that the walkout has to be dug four feet below the basement floor level, it can be quite deep, which poses not only water risks but also risks of collapse during excavation. This is why I always fill the excavated part of the walkout with concrete. It provides the most stable surface to build the walkout and exterior adjoining wall on, and also speeds the process of forming the walls (otherwise they have to form a wall, pour it, wait, come back, strip footings, waterproof then do it all again.
Here was the first of 3 9-meter full concrete trucks to deposit their load in the giant walkout at 150 Van Dusen...