Friday, March 10, 2017

Garage and walkout slabs

Thom finished off his concrete work today, with the walkout and garage slabs being last on his to-do list. 


Thursday, March 9, 2017

HVAC Starts

Pinewood started the 2nd floor HVAC system this morning.  We are going with 2 systems in the house, which makes for a very efficient heating and cooling combination, while eliminating all bulkheads in the first floor area.



Wednesday, March 8, 2017

Concrete slab

The concrete slab in the basement is steaming as it cures.  The walkout, although a big pain during excavation and foundation, really makes managing the helicopter for finishing the concrete very easy.


Tuesday, March 7, 2017

House wrap

Junior and his team arrived to wrap the house in preparation for the masonry on the house exterior.